Sanitary Sewer Lining Project

About the Project

The City of New Brighton has awarded a contract to Insituform Technologies USA, Inc., to improve the mainline sanitary sewer pipe that serves the neighborhood show on the map above. The existing sanitary sewer is a clay pipe that has become prone to root intrusion and groundwater infiltration, which leads to unnecessary and expensive treatment of “clean” water.

Project Schedule

Cleaning/Televising/Measuring: May 2nd – May 6th  

CIPP Lining Process: May 23rd – May 27th

Manhole Rehabilitation and Service Lateral Lining: June 1st – June 22nd

Learn More

More: Current News