2020 Street Rehabilitation

map of streets

Improvement Project 20-1, 2020 Street Rehabilitation includes Valley View Lane, Knollwood Drive, Eastman Drive, Gregory Drive, Longview Drive, and Robin Lane.


This project will include the following components: 

  • Pavement and base material removal and replacement
  • Spot curb and gutter replacement 
  • Fire hydrant replacement
  • Catch basin replacement
  • ADA pedestrian ramp improvements


These streets are identified in the City’s Capital Improvement Plan for rehabilitation in 2020. All construction activities for this project will be done under a publicly bid contract by a private contractor. The Department of Community Assets and Development will administer the contract and provide the engineering services.

Project Update (Sept. 25, 2020)
Project Update (Sept. 11, 2020)
Project Update (Sept. 4, 2020)
Project Update (Aug. 28, 2020)
Project Update (Aug. 21, 2020)

Public Hearing Presentation


Feasibility Study

Informational Meeting Presentation


Project Contacts
 Steven Toso
 Site Representative
 651.638.2053
steven.toso@newbrightonmn.gov


Dustin Lind
 Engineering Supervisor
 651.638.2055
dustin.lind@newbrightonmn.gov

Craig Schlichting
 Director of Community Assets and Development
 651.638.2056
craig.schlichting@newbrightonmn.gov

To report an issue or concern about street reconstruction online: